Commissioning and diagnostics
4-3
ET 200eco Distributed I/O Station
A5E00158716-02
4.2
ET 200eco commissioning and startup
Software requirements
Table 4-2
Software required for commissioning
Configuration
software used
Version
Notes
STEP 7
V4.02 or higher
You have implemented the GSD file for ET 200eco in
STEP 7.
V 5.1 or higher;
ServicePack 4
The GSD file is included in the scope of delivery.
COM PROFIBUS
V3.0 or higher
You have implemented the GSD file for ET 200eco in
COM PROFIBUS.
Configuration software
for the DP master
used
You require the GSD file for ET 200eco.
Prerequisite for commissioning
Table 4-3
Prerequisite for commissioning the ET 200eco
Prior activity
See...
1. The DP slave is installed
2. The PROFIBUS address is set at the DP slave
3. The DP slave is wired
4. The DP slave is configured
5. The power supply to the DP master is switched on
The DP master manual
6. The DP master is set to RUN mode
The DP master manual
Commissioning ET 200eco
Table 4-4
Steps for commissioning the DP slave
Step
Procedure
1.
Switch on the electronic/sensor power supply to the DP slave.
2.
If required, switch on the load voltage supply.
Summary of Contents for SIMATIC ET 200eco
Page 8: ...Preface viii ET 200eco Distributed I O Station A5E00158716 02 ...
Page 18: ...Product overview 1 6 ET 200eco Distributed I O Station A5E00158716 02 ...
Page 70: ...Commissioning and diagnostics 4 16 ET 200eco Distributed I O Station A5E00158716 02 ...
Page 116: ...I O address area C 6 ET 200eco Distributed I O Station A5E00158716 02 ...
Page 124: ...Index Index 4 ET 200eco Distributed I O Station A5E00158716 02 ...