
7 Getting Started
7.7 Commissioning
123
SICAM Q100, 7KG95xx, Device Manual
E50417-H1040-C522-A6, Edition 06.2019
✧
Switch on the supply voltage of the device.
After an operating time of approximately 15 minutes, the device will stay within the tolerances specified in
the technical data.
✧
Switch the alternating voltages and alternating currents to be measured at the measuring object on the
measuring lines.
✧
Carry out the measurements as described in chapter 9 or chapter 10.
7.7.2
Changes During Operation
The device is designed for permanent operation.
If you want to change the measurement setup, for example by connecting terminals so far unused, proceed
analogously to the Initial Commissioning.
NOTE
The device does not have a power on/off switch. Switch the supply voltage on or off directly at the respective
supply cable.
NOTE
If you change the measurement setup, de-energize the supply voltage lines and all measuring lines before
opening the control cabinet. Note the warnings in chapter 7.7.1.
MAN_SICAM_Q100_US.book Page 123 Wednesday, June 5, 2019 9:31 AM