Engineering via SICAM TOOLBOX II
204
SICAM RTUs, SICAM AK 3 User Manual
Edition 07.2016, DC2-028-2.03
4.2.3
Commissioning
and
Test
4.2.3.1 Loading Program Code
To load the program code (compiled FUD) into the target system, the engineering PC must be
connected with the target system (see
The loading of the program code into the target system takes place jointly with the parameters
set in the "OPM II". Thereto the tool "Parameter Loader" must be used (see also section
Caution
During a loading operation, a power down of the master control element is to be absolutely avoided, since
the data on the flash card could be destroyed as a result.
You find the technical description thereto in the manual
SICAM RTUs Common Functions
System and Basic System Elements, chapter "Automation", section "Open-/Closed-Loop Con-
trol Function", "Loading of Application Program (Reload)"
.
You find the instruction for the operation in the
SICAM TOOLBOX II Online Help, chapter
"Service Programs", section "Parameter Loader"
.
Note
Instead of a function diagram an instruction list (ASCII format) can be imported in "CAEx
plus
".
4.2.3.2 Test Functions
4.2.3.2.1 Simulate Function Diagram Offline
The logic operations of a function diagram can be tested in "CAEx
plus
" with the
offline
Simulation
.
This function can be called via the context menu of the basic system element, program in-
stance or type instance (right mouse button). You can find the details thereto in the
CAEx plus
User Manual, chapter "Additional Products", section "Offline Simulation"
.
Summary of Contents for SICAM AK 3
Page 8: ...Open Source Software 8 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...
Page 84: ...Installation 84 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...
Page 166: ...System Components 166 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...
Page 180: ...Prepare Engineering 180 SICAM RTUs SICAM AK 3 User Manual Edition 07 2016 DC2 028 2 03 ...