Commissioning
2015-10-12
2 Commissioning
This section describes how to commission the Web Server.
2.1 Prerequisites
The following conditions must be met to commission the Web Server:
·
The Web Server is mounted and wired (see Installation instructions, G5701).
·
The connected KNX devices are commissioned.
·
The KNX devices have a valid KNX address [1...253] are operating.
Note: Web Servers are delivered with KNX address 150. As a result KNX
address range [1…253], except for 150, applies to all other devices.
·
Bus power supply to the KNX bus is available.
·
The Web Server or another KNX device is the clock master on KNX.
·
The Web Server automatically receives its IP address from the router when the
DHCP client is switched on. The address without router is:
192.168.2.10
(factory setting, see Section 8.1.2)
·
Connecting a SmartPhone App to a Web Server makes sense only after the
Web Server is fully commissioned.
The following is required to commission the Web Server on the portal:
·
The Web Server is connected to the Internet
The Web Server automatically registers on the portal.
The operation LED starts to flash green / orange as soon as the Web Server is
connected to the portal.
The following is required to commission the Web Server:
·
A PC/laptop and a web browser commission Web Server via an USB interface.
The RNDIS driver must be installed to connect via USB. IP address USB:
192.168.250.1 (cannot be changed). The address range 192.168.250.1 -
192.168.250.255 cannot be used for Ethernet and is reserved exclusively for
USB.
·
The RNDIS driver is automatically installed when connecting via USB if the
PC/laptop is connected to the Internet (as long as the Microsoft online update
service is enabled). The RNDIS driver can be installed manually if there is no
connection to the Internet (see Section 11.3.3)
·
The RNDIS is supplied on the Web Server at http://<IP-Adresse>/drivers/
·
To navigate, always start with primary navigation, then use the secondary
navigation to select the desired menu item.
·
Return: Click
"Upward" or navigate via the path or primary navigation.
General
Notes
Portal commissioning
requirements
Local commissioning
requirements without
portal
Operating notes