2 Commissioning
This section describes how to commission the web server.
2.1 Prerequisites
The following conditions must be met to commission the web server:
Prerequisites
•
The web server is mounted and wired (see Installation instructions, G5711).
•
OZS164.23 only: The SIM card is inserted.
•
The connected bus device is commissioned.
•
The bus device has a valid address and is operational.
•
The bus device works troublefree; the fault LED is not lit.
•
The bus power supply to the bus device is turned on.
•
Recommended by clock time supplier: The LPB bus device is clock slave with
remote setting.
•
IP address USB:
192.168.250.1
(unchangeable)
•
IP address Ethernet:
192.168.251.1
(ex works)
Notes
11 / 108
Siemens Web
server
CE1C5711en
Building Technologies
Commissioning
25.08.2010