Commissioning Guidelines
1st step: Install ASM in STEP 7
S
ASM 475, 473: The installation program for the ASM 475, 473 must be
executed once on the STEP 7 PC.
S
PROFIBUS-ASM: The device master file (Siem80B6.GSD for ASM 452)
must be linked to the device catalog with HW Config (Extras/Neue GSD
installieren ...).
2nd step: Configure hardware in STEP 7
The configuration varies depending on which MOBY ASM is being used.
S
ASM 475: Central setup on S7-300
S
ASM 475, 473: Distributed setup with PROFIBUS and ET 200M, ET 200X
S
ASM 452: Distributed setup with PROFIBUS
The following figure shows the placement of the MOBY ASMs in the hardware
catalog.
ASM 475 in
central setup
Example: ASM 475 in
distributed setup with
ET 200M
ASM 452 in distributed
setup with PROFIBUS
Figure 8-1 Placement of the MOBY ASMs in the hardware catalog
When placing the ASMs, make sure that the I address and the Q address have the
same values. The value in the “I address” field must be used later in the STEP 7
project as the ASM_address variable. If a MOBY ASM has more than one channel
(e.g., ASM 475 = 2 channels), the same I address must be used for every channel.
The following figure shows an example of a hardware: configuration.
8
Summary of Contents for MOBY FC 56
Page 12: ...Introduction 1 6 FC 56 J31069 D0155 U001 A0 7618 ...
Page 63: ...5 1 FC 56 J31069 D0155 U001 A0 7618 Sample Applications 5 ...
Page 80: ...Sample Applications 5 18 FC 56 J31069 D0155 U001 A0 7618 ...
Page 90: ...Entry Exit Check of an MDS in an SLG Field 6 10 FC 56 J31069 D0155 U001 A0 7618 ...
Page 94: ...System Configuration 7 4 FC 56 J31069 D0155 U001 A0 7618 ...
Page 100: ...Commissioning Guidelines 8 6 FC 56 J31069 D0155 U001 A0 7618 ...
Page 101: ...9 1 FC 56 J31069 D0155 U001 A0 7618 Error Messages and Trouble Shooting 9 ...
Page 152: ...Programming MOBY ASM on PROFIBUS DP V1 B 30 FC 56 J31069 D0155 U001 A0 7618 ...