3. INSTALLATION – MIDIMASTER Vector
English
© Siemens plc 1999
G85139-H1751-U529-D1
25
4/8/99
3.
INSTALLATION - MIDIMASTER Vector
3.1 Mechanical Installation
WARNING
THIS EQUIPMENT MUST BE EARTHED.
This equipment must
not
be energised with the cover removed.
To guarantee the safe operation of the equipment it must be installed and commissioned properly by qualified personnel
in compliance with the warnings laid down in these operating instructions.
Take particular note of the general and regional installation and safety regulations regarding work on high voltage
installations (e.g. VDE), as well as the relevant regulations regarding the correct use of tools and personal protective gear.
Mount the inverter vertically to a flat, non combustible surface. Make sure that the unobstructed clearance for each of the
cooling inlets and outlets above and below the inverter is at least 100 mm.
Environmental requirements are described in section 1.1
The MIDIMASTER Vector must be secured to a suitable load-bearing wall by M8 bolts, washers and nuts. Frame size 4, 5 and 6 units
need four bolts. Frame size 7 units should be lifted using the two lifting holes and secured by six bolts.
W
H
D
D
W
H
W
H
D
W
H
D
Figure 3.1.1: MIDIMASTER Vector - Frame Size 4, 5, 6 and 7