Mammomat 1000/3000
Register 3
SP B7-230.033.07
Page 2 of 10
Siemens-Elema AB
Installation and Start-Up
Rev. 03
11.99
SPS-UD
Solna, Sweden
18 - 2
Final procedures
Removing the measuring instruments
18
1.
Turn OFF the generator.
2.
Remove the service PC.
3.
Remove connected measuring instruments.
Checking the protective grounding resistance
18
Using the protective ground-wire tester, measure the resistance between the protective
ground terminal in the stand (X899, see Chapter 5 "Cable connections") and all metallic
parts of the equipment which the patient/operator may come in contact with, incl. all object
tables. The protective ground resistance must not exceed 0.1
Ω
.
Mounting the cable duct covers
18
If not already done, mount the cable duct covers, see Chapter 4 "Installing the generator
and the stand".
Mounting the stand covers
18
The Mammomat stand covers exist in two versions, one with separate rear side covers
and one with a single rear cover that also covers the rear sides.
When mounting the stand covers, make sure that the screws at
the top of the stand are securely tightened and have functioning
contact washers. These screws are used to establish protective
ground connections. Before mounting the front covers, be sure to
remove the protective strips from the metal curtain (2). Store the
strips in the holders provided on both sides of the curtain.
WARNING