Procedure
1. Lift the machine using two separate beams and crane trolleys
①
.
2. Leave the drive-end beam in place and continue to lift the rotatable non-drive-end beam
until the machine reaches its center of gravity and the drive-end beam is unloaded
②
.
3. Remove the drive-end lifting beam. Rotate the machine through 180°. When doing this,
take care not to damage any attached parts.
4. Place the free beam on the lifting eyes provided and lift the machine using this beam until
it is perpendicular to the base
③
.
ᆰ
ᆱ
ᆲ
r
Image 5-1
Erecting the motor
Turning the machine on to its side
To lay the machine on its side, proceed in the reverse order.
5.4.6
Removing anti-corrosion protection
Machined, bare metal surfaces of machine parts and small components such as screws, bolts,
wedges, feather keys, and dowel pins, are treated with an anti-corrosion agent.
Carefully remove the anti-corrosion agent and immediately start the installation work.
Assembly
5.4 Lift the machine to where it will be installed, and position it
LOHER CHEMSTAR 1PS2
Operating Instructions 08/2016
45
Summary of Contents for LOHER CHEMSTAR 1PS2
Page 2: ...04 08 2016 11 45 V3 00 ...
Page 64: ...Electrical connection 6 2 Connecting LOHER CHEMSTAR 1PS2 64 Operating Instructions 08 2016 ...
Page 74: ...Start up 7 8 Test run LOHER CHEMSTAR 1PS2 74 Operating Instructions 08 2016 ...
Page 84: ...Operation 8 11 faults LOHER CHEMSTAR 1PS2 84 Operating Instructions 08 2016 ...
Page 102: ...Maintenance 9 2 Corrective Maintenance LOHER CHEMSTAR 1PS2 102 Operating Instructions 08 2016 ...
Page 118: ...Service and Support LOHER CHEMSTAR 1PS2 118 Operating Instructions 08 2016 ...
Page 120: ...Technical data and drawings LOHER CHEMSTAR 1PS2 120 Operating Instructions 08 2016 ...
Page 142: ...Index LOHER CHEMSTAR 1PS2 142 Operating Instructions 08 2016 ...