Mounting / Installation
5
Installing the reflectors for middle distance and short distance (foil)
62
Building Technologies
007016_i_en_--
Fire Safety
2012-09-07
2. If necessary screw the M20 x 1.5 metal cable gland into the openings.
3. Install the base with two screws on a level surface.
4. Insert the cable for the 24 V supply into the base.
5. Connect the wires to the terminals for the heating unit (3) according to the
connection diagram.
6. Install the prism unit (2) on the base with four screws.
See also
5.5
Installing the reflectors for middle distance and
short distance (foil)
WARNING
Danger of falling
Bodily injury
● When installing, use a secured ladder or work platform.
The installation location of the reflector is defined according to the planning
information.
Install the reflector with one screw on a level surface. The diameter of the hole
is 4 mm.