Air sampling smoke detection system
AD1-C11

Quick Guide for Commissioning

1 Installation

§

  Connect power (24VDC)

§

  Connect the detector line

§

  Connect reset input (if S1 = ON)

§

  Install the detector base and the smoke detector

§

  Connect pipe system or test pipe

2 Set 

Up

Set DIP switches S1 and S2 on pcb E573 according to tables below:

Air flow monitoring

switch 

S2

delay time

switch 

S2

range

A

B

C

D

OFF

ON

short

30 s

ON

OFF

small

I

ON

OFF

middle

2 min.

 (standard)

OFF

ON

middle

II

ON

ON

long

16 min.

OFF

OFF

large

III        

(standard)

OFF

OFF

very
long

128 min.

Fault

switch S1
OFF

Fault not latching        

(standard)

ON

Fault latching until reset

3 Commissioning

Adjustment of the Air Flow Sensor

1.

Fix cover and tighten screws

2.

The unit must be in operation for at least 5 minutes

3.

Adjustment with adjusting peg to

0V  +- 15 mV

or according to the air pressure adjustment
chart

4.

Unit ready

Fire & Security Products

Siemens Building Technologies Group