7 | Installation
126/174
8DJH • Installation and Operating Instructions • Version 11 • 500-8384.9
On the following panel types, the cable compartment cover is bolted on additionally:
▪ Metering panel
▪ Cable panel
▪ Panel with pressure absorber system (IAC up to 21 kA)
Removing the cable compartment cover
1. Earth the feeder.
2.
For cable panels or panels with a pressure absorber system (IAC up to 21 kA)
: Remove 2
self-tapping bolts
2
at the top of the cable compartment cover.
For metering panels:
Undo 4 self-tapping bolts
2
and 12 bolts
3
at each cable
compartment cover.
3. Lift the cable compartment cover
1
and remove it to the front.
2x
4x
12x
Fig. 166:
Cable compartment cover, all panel
types (without metering panel)
Fig. 167:
Cable compartment cover,
metering panel
1
Cable compartment cover
2
Self-tapping bolt M6x50
3
Hexagon head bolt with hexalobular socket and small flange M6x16
Hooking the cable compartment cover in
1. Hook the cable compartment cover in from above.
2.
If the cable compartment cover was bolted on:
Fasten the cable compartment cover again
at the panel using the bolts removed previously.
7.22.2 Removing and mounting the cross member
NOTICE
Removed cross member
If the cross member was removed, the bracing required for the stability of the switchgear is
missing. The switchgear can be distorted by movement.
⇨ If the cross member is removed, do not move the panel.
Removing the cross member
1. Remove the cable compartment cover [
Page 125, "Removing and mounting the cable
2.
Panel height 1200 mm:
Undo 4 bolts
2
at the cross member
1
.
3.
Panel height 1400 mm:
Undo 6 bolts
2
at the cross member
1
.
4.
Metering panel:
Undo 10 bolts
4
at the cross member
1
.
5. Undo the floor fixing bolt
3
if the panel was already fastened to the foundation.
6. Remove the cross member