INSTALLATION
5
5.5.1
Cable inlet on the system cabinet
The cable ducts on the PowerCEMS100 system cabinet are located on the top of the
control cabinet.
The system-specific version of the PowerCEMS100 system cabinet may vary, refer to the
view drawings (see
) and/or the Technical System Documentation.
5.5.2
Preparing the main power supply
▸
Lead the main power supply to the system cabinet.
▸
The wiring system to the power voltage supply of the system must be installed and fused
according to the relevant power voltage regulations.
▸
Provision of UPS (option).
▸
Before commissioning, check the main power supply properties for rated current/rated
voltage/rated capacity for system supply (auxiliary power) match the system-specific
specifications of the PowerCEMS100 analysis system
5.6
External components and signal generators
Carry out electrical and mechanical connection of project-related external components and
signal generators and other project-specific peripherals to be integrated and then put
these into operation.
5.7
Connecting to the customer plant
▸
Lay all necessary connections according to the Technical System Documentation:
– Voltage supply
– Signal lines
– Integration of all external components
Refer to the terminal diagram in the Technical System Documentation for a
description of the terminal strips.
Refer to the system-specific wiring diagram and corresponding Data Sheets or
Operating Instructions of the respective external components for details on the
main power supply connection or connection to the PowerCEMS100 analysis
system as well as specifications on auxiliary power required (rated current/