Commissioning
6
Commissioning
No PC is required for initial commissioning.
WARNING
Do not commission without testing by qualified safety personnel
Before you commission the system for the first time, you must have it checked and
approved by qualified safety personnel. Observe the notes provided in Chapter
6.1
Launching the system
All system components are automatically launched when starting the truck and checked in
a self-test.
Fig. 43: Self-test of the system on the operator display
The system is ready for operation after approx. 60 seconds. A notification appears
informing you that the system has not yet been (completely) configured.
Fig. 44: Information about incomplete configuration
Warnings (optical and acoustical) may occur as the system setup is yet to be done. This is
no malfunction and can be ignored.