Chapter
6
Operating Instructions
Flexi Soft Gateways
116
© SICK AG • Industrial Safety Systems • Germany • All rights reserved
8012664/XB29/2013-06-11
Subject to change without notice
Fieldbus gateways
6
Fieldbus gateways
6.1
PROFIBUS DP gateway
The following Flexi Soft gateway can be used for PROFIBUS DP: FX0-GPRO.
6.1.1
Interfaces and operation
Controls and status indicators
LED
Meaning
Connection to DP master established
BF
Red
No bus connection: Fieldbus cable break, address fault
or master is not (or no longer) writing to the bus
Power-up, waiting for bus off
Green Executing
Green Idle
Red/green
Executing, but there is an error at the gateway
Red
1 Hz: Configuration required or in progress
2 Hz: Critical fault on gateway
MS
Red
Critical fault on another module
No power supply
Green
Power supply switched on, no error
PWR
Red Critical
fault
Fig. 56: Controls and status
indicators FX0-GPRO
Tab. 83: Meaning of the
status LEDs of the FX0-GPRO
Symbol description:
: LED is off
Green: LED lights up green
Red: LED flashes red
Address switch 1
Address switch 2
PWR LED (red/green)
PROFIBUS connection
MS LED (red/green)
BF LED (red)