8
The ICE is typically equipped with the SHOCKWAVE AUTOTUNE system that allows for simple filling and setting of the
ICE system. To get the most out of your ICE, it is important to always setup the suspension properly when weight is either
added or removed from the ICE.
STEP 1:
Ensure the ICE is set up with its full occupants and gear weight in place.
STEP 2:
If the red ‘WAIT’ light is illuminated the compressor is running to fill up the air tank. This can take up to 5
minutes. Once the green ‘READY TO FILL’ light is illuminated the air tank is full.
STEP 3:
Lift and hold the momentary toggle switch in the ‘FILL’ position to fill all shocks. Hold the switch until the ICE is
at full height.
STEP 4:
Set the ICE console to ‘SET’ height by holding the switch in the ‘SET’ position. This generally takes 5-10 seconds.
STEP 1:
Ensure the ICE console is set up with its full occupants and gear weight.
STEP 2:
Lift the ‘ON/OFF’ toggle switch to the up position. The ‘FILL’ light should be blinking.
STEP 3:
Lift the ‘FILL’ toggle switch to the up position and wait until the ‘FILL’ light has stopped blinking.
STEP 4:
When the system is ready, the ‘SET’ light will be flashing. At this time hold the ‘SET’ toggle down until the light
stops blinking. At this point the ‘STATUS’ light should be solid green in the “READY” state.
USING AUTOTUNE 1 SYSTEM
USING AUTOTUNE 2 SYSTEM
1
LOAD OCCUPANTS AND GEAR INTO ICE
2
WAIT UNTIL GREEN LED IS ILLUMINATED
3
‘FILL’ UNTIL ICE IS AT FULL HEIGHT
4
TOGGLE SWITCH TO ‘SET’ UNTIL ICE SETTLES
5
TO LOWER ICE, PRESS AND HOLD ‘DRAIN’
INSTRUCTIONS
WAIT
READY TO FILL
DRAIN
SET
FILL
USING AUTOTUNE SYSTEM