First commissioning
Before the first commissioning, please check:
•
Whether the drives are undamaged.
•
The entire wiring (control) for completeness, short circuit and ground faults.
•
Whether the phases of the line voltage and the motors are connected correctly.
•
Whether the control and message rail phases are connected correctly (communica-
tion type: rail bus).
•
Whether the saved configuration is valid for the application.
•
Whether the uploaded parameters are optimally aligned to the motors.
Information about normal operation - handheld control (HBG) not connected
If the handheld control is
not
plugged in, the safety contacts must be bridged.
Other-
wise, automatic operation (standard operation) is not possible (control doesn’t
move / axis 1 (X2.1 & X2.2) blocked or no voltage output)!