background image

                                                                      

 

 

   

 

 

 

 

S

EPARATE 

P

LACING 

B

OOMS 

SPB 

 

Summary of Contents for SPB 25

Page 1: ...SEPARATE PLACING BOOMS SPB...

Page 2: ...ructions 12 1 5 1 General points to consider when using placing booms 12 1 5 2 Safety aspects 13 1 5 3 TOOLS REQUIRED FOR ASSEMBLY 15 1 6 Working range 16 1 6 1 SPB 25 16 1 6 2 SPB 28 17 1 6 3 SPB 32...

Page 3: ...concrete Added time savings are realized by the tower crane being free to handle other lifting operations Years ago already the trend to rationalization and short completion periods led to the use of...

Page 4: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 3 1 2 Installation method Free standing up to 20 m Through the floor slabs Directly on cross frame...

Page 5: ...ans of hand levers or installed electric remote control cable end hose and connecting line for connection to the delivery pipeline Trestle pin connection for quick separation when repositioning the pl...

Page 6: ...pipeline DN 125 Horizontal reach from centre of rotating axis max 28 m Slewing range folding 530 Length of end hose 4 m Electric engine power 400 V 50 cps protection mode IP 44 30 kW Total weight of...

Page 7: ...with hydraulic oil with pin connection on main boom to reduce handling weight 2 Accessories Supplemental Equipment for Concrete Placing Boom 1x Tubular head part 638 Kg for SPB 28 and 32 849 Kg for S...

Page 8: ...5 m above the last floor frame 1x Hydraulic climbing device 75 Kg each cylinder for automatic lifting of the tubular mast and placing boom consisting of 1 set climbing cylinders actuated by means of a...

Page 9: ...h back protection 3 Climbing procedure During the climbing operations the boom column must be guided and supported by three climbing guide frames These frames transfer the occurring forces into the co...

Page 10: ...When the climbing cylinders are fully extended insert a supporting pin 1 Fig 2 on both sides above the guide frame 5 The safety latches 2 Fig 2 of the supporting pins must be inserted into the next hi...

Page 11: ...op When this position is reached the climbing equipment and the climbing guide frame must be relocated Fig 1 if climbing is to continue To do so Move the climbing equipment to the next higher floor an...

Page 12: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 11...

Page 13: ...ion must be paid to the condition of the machine while on site it must be inspected regularly by a competent person and a report placed in the safety file 7 The site electrician should inspect on a re...

Page 14: ...working area needs to be properly cordoned off and clear of any trip hazards It needs to be of sufficient size to allow ease of access and egress for the assembly personnel Every operative must wear t...

Page 15: ...crete delivery pipeline is approximately 5 500 kg A crane of sufficient capacity is required for the operation of lifting the column on top of the heavy duty cross frame Otherwise the column must be a...

Page 16: ...THE FIXINGS ON THE WORKING PLATFORM AND TRAP DOOR ASSEMBLY 3 HAMMER FOR DRIVING IN OUT THE CONNECTION PINS ON THE BOOM TO MAST CONNECTION OR THE BOOM ARM TO TURRET CONNECTION 4 HYDRAULIC TORQUE WRENCH...

Page 17: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 16 5 Working range 5 1 1 SPB 25...

Page 18: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 17 5 1 2 SPB 28...

Page 19: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 18 5 1 3 SPB 32...

Page 20: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 19 5 1 4 SPB 35...

Page 21: ...G GMBH Separate Placing Booms SPB 02 2014 20 6 Examples for load drawings Please note that in case of other dimensions on site new Load calculations have to be made and adapted to the real situation o...

Page 22: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 21 6 1 1 SPB 25 in slab distance 3m no counterweight...

Page 23: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 22 6 1 2 SPB 28 freestandig with 18m column no counterweight...

Page 24: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 23 6 1 3 SPB 28 freestandig with 18m column with counterweight...

Page 25: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 24 6 1 4 SPB 28 in slab distance 3 2m no counterweight...

Page 26: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 25 6 1 5 SPB 32 in slab distance 4 0m no counterweight...

Page 27: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 26 6 1 6 SPB 35 in slab distance 4 5m no counterweight...

Page 28: ...SCHWING GMBH Separate Placing Booms SPB 02 2014 27 Solutions for concrete...

Reviews: