3.5
Commissioning check list
Mechanical check
Are all suction pipes installed as specified in the installation
drawing?
□ yes / □ no
Are all fittings fastened and tight?
□ yes / □ no
On installations with siphon blocks: Are all siphon blocks filled
with oil and all un-used openings closed?
□ yes / □ no
On installations with pipe siphon: Are all siphons filled with oil?
□ yes / □ no
On installations with oil separator: Is the separator filled with
oil?
□ yes / □ no
Is the negative pressure at the measuring head adjusted to 60
mmWC?
□
yes / □ no
Adjusted negative pressure
mmWC
Is the screw removed from the control cover
□ yes / □ no
Electrical check
Is the power supply connected to the terminal and is the
voltage within the specified range?
□
yes / □ no
Measured supply voltage
Volts
Is the monitoring device installed?
□
yes / □ no
Are the
‘
Alarm
’
and
‘
Ready
’
signals connected to the engine
control and safety system?
□
yes / □ no
Are the correct wire break resistors installed
□ yes / □ no
Value of wire break resistor
kOhm
Is the correct interface mode at pin 11 and 13 selected?
□ yes / □ no
Functional check
On vessels perform the on-board test with test plate. Test
positive?
□ yes / □ no
At engine factory perform smoke test. Test positive?
□ yes / □ no
As an alternative to the smoke test, measure the negative
pressure at the end of the suction pipes. Values as specified?
□ yes / □ no