Troubleshooting

Problem

Possible cause

Solution

The unit does not cool or heat suffi-
ciently

Primary air volume not present or too low

Check primary air volume

Air inlet and outlet of the inner unit clogged

Remove foreign material and clean the unit

Air in the hydraulic system

Ventilation of the hydraulic system
Please inform the installer

Installed unfavourable or malfunctions at the temperature
control or sensor

Install thermostat in a different place

Clogging of the cooling/heating register

Clean the register in accordance with the
maintenance instructions

The unit is losing water

Condensate in the register

Modify the register water inlet temperature

The water circuit of the register is leaking

Please inform the installer

Register damaged
Incorrect valve or hydraulic connection

The unit is working with too much
noise

The air intake or air blow openings or the lines are clogged. Remove foreign material and clean the unit

Loose screws and fastening elements

Tighten screws

Foreign material or dirt on register surface

Remove foreign material by careful 
brushing

Primary air volume too large for selected configuration.

Check primary air volume

Summary of Contents for DISA-360

Page 1: ...Ferdinand Schad KG Steigstra e 25 27 D 78600 Kolbingen Telephone 49 0 74 63 980 0 Fax 49 0 74 63 980 200 info schako de www schako de Installation Mounting and Maintenance DISA 360...

Page 2: ...ered model 4 Function 4 Installation and commissioning 5 Operating conditions 5 Material reception 5 Transport lifting and handling 5 Storage 5 Installation 6 Mounting 6 Hydraulic connections 6 Connec...

Page 3: ...lacement of defec tive materials Recycling The inspection installation hydraulic connection and com missioning of the device must be carried out by qualified skilled personnel only in compliance with...

Page 4: ...ing or optionally 4 pipe system cooling and heating The registers consist of cop per pipes 12 mm in thickness aluminium ribs and a steel frame Grille 3 Possible designs perforated sheet grille made of...

Page 5: ...Foldable perforated sheet perforation 6 mm B Nozzle configuration B 592 total width 592 mm 592 total length 592 mm WS1 Water connection left H Connection horizontal AS1 Number of connecting pieces 1 c...

Page 6: ...void excessive tighten ing or twisting of the register connections Make sure that places that are intended as openings for air admission and air discharge are free of pipes electric ca bles crossbeams...

Page 7: ...ends on the select ed model Please follow the instructions enclosed with each model Adjustment of the air deflection blades To regulate the air flow ro tate the air deflection blades manually With blo...

Page 8: ...by spraying it with a non aggressive cleaner Hydraulic connections were tightened properly and exhib it no leaks Connecting and fastening elements have been sufficiently tightened Adequate access for...

Page 9: ...lean it by spraying it with water or compressed air or by evacua tion Please do not use any scouring agents for cleaning since these materials may impair or damage the DISA 360 gal vanised steel alumi...

Page 10: ...e nozzles at the primary air plenum box see drawing and the other end is con nected to the hose connection of a Pa meter The values read on the meter and the following formula can be used to to determ...

Page 11: ...or Install thermostat in a different place Clogging of the cooling heating register Clean the register in accordance with the maintenance instructions The unit is losing water Condensate in the regist...

Reviews: