–22–
3-14. “ASSY,CHASSIS R
(7A000) ”, “COMPL,
PIPE DRUM RUBBER
(4A000) ”,
“COMPL,GUIDE,PAPER
(5I000) ”,
“CAM,MECHANISM R
(5L000) ”, and
“CAM,MECHANISM L
(5K000) ”
(See Figs. 3-14-1 to 3-14-4)
1)
Referring to sections 3-1 through 3-13, remove each part.
2)
Remove the “SPECIAL WASHER-7.1X0.8
(4B000)
”.
(Refer to Fig. 3-14-3.)
3)
Remove the “SCR S-TPG BIN 2.6X4
(3B200)
” on the
“ASSY,CHASSIS R
(7A000)
” side. (Refer to Fig. 3-14-2.)
4)
Remove the two “SCR S-TPG BIN 2.6X4
(6P300)
” on the
“ASSY,CHASSIS R
(7A000)
” side. (Refer to Fig. 3-14-2.)
5)
Pull connector 1 and connector 2 out from each hole.
(Refer to Fig. 3-14-2.)
6)
Place the “ASSY,CHASSIS L
(7C000)
” down and remove
the “ASSY,CHASSIS R
(7A000)
”.
7)
Pull out the “SHAFT,PULLEY FIX
(4E000)
” and remove
the two “WASHER Y 8X16X0.25
(4C000)
” and the
“SPRING,PRESSURE DRUM
(4D000)
”. (Refer to Fig.
3-14-1.)
8)
Remove the “COMPL,PIPE DRUM RUBBER
(4A000)
”,
“COMPL,GUIDE,PAPER
(5I000)
”, “CAM,MECHANISM
R
(5L000)
”, and “CAM,MECHANISM L
(5K000)
”.
ASSEMBLY NOTES:
1.
Apply grease (VJ8-0229) as shown in Fig. C of Fig.
3-14-3.
2.
Install the “COMPL,GUIDE,PAPER
(5I000)
” and
“CAM,MECHANISM L
(5K000)
” into the “COMPL,PIPE
DRUM RUBBER
(4A000)
”. Install the “CAM,
MECHANISM L
(5K000)
” so that shaft 1 and shaft 2 on the
“COMPL,GUIDE,PAPER
(5I000)
” are set into the slots as
shown in Fig. D of Fig. 3-14-3.
3.
Install the assembly (“COMPL,GUIDE,PAPER
(5I000)
”,
“CAM,MECHANISM L
(5K000)
” and “COMPL,PIPE
DRUM RUBBER
(4A000)
”) completed in step 2 to the
“ASSY,CHASSIS L
(7C000)
” as shown in Fig. F of Fig.
3-14-4.
4.
Install the “CAM,MECHANISM R
(5L000)
” so that shaft 3
and shaft 4 on the “COMPL,GUIDE,PAPER
(5I000)
” are
set into the slots as shown in Fig. E of Fig. 3-14-3.
5.
Install the “ASSY,CHASSIS R
(7A000)
” as shown in Fig.
G of Fig. 3-14-4.
6.
Pass connector 1 and connector 2 through hole 1 and hole
2 on the “ASSY,CHASSIS R
(7A000)
” respectively, and
put portion A and portion B over hole 1 and hole 2
respectively. (Refer to Fig. 3-14-2.)
7.
Insert dowel 1 into slot 1 and insert dowel 2 into hole 3 as
shown in Fig. 3-14-2. (About slot 1 and hole 3 on the
“GUIDE,PAPER EXIT
(6P100)
”, refer to Fig. A of Fig.
3-14-2.)
8.
Insert dowel 3 into hole 4 and insert dowel 4 into hole 5 as
shown in Fig. 3-14-2. (About hole 4 and hole 5 on the
“GUIDE,CASSETTE R
(3B100)
”, refer to Fig. B of Fig.
3-14-2.)
9.
Install the two “SCR S-TPG BIN 2.6X4
(6P300)
” and the
“SCR S-TPG BIN 2.6X4
(3B200)
”, then install the
“ASSY,CHASSIS R
(7A000)
”.
10. Do not allow dust or the trash to stick to the surface of the
“COMPL,PIPE DRUM RUBBER
(4A000)
”.
11. Referring to section 3-9, align phase between the “CAM,
MECHANISM R
(5L000)
” and the “CAM,MECHANISM L
(5K000)
”.
12. Referring to section 3-6, adjust the tension of the
“BELT,MOTOR STEP
(4J000)
”.
13. Referring to section 3-7, adjust the tension of the
“BELT,DRUM
(4I000)
”.
SHAFT,PULLEY FIX
(4E000)
WASHER Y
8X16X0.25
(4C000)
SPRING,PRESSURE
DRUM
(4D000)
Fig. 3-14-1
SCR S-TPG
BIN 2.6X4
(3B200)
SCR S-TPG BIN 2.6X4
(6P300)
ASSY,CHASSIS R
(7A000)
Fig. A
Hole 3
Slot 1
Dowel 4
Dowel 3
Dowel 2
Dowel 1
Hole 1
Hole 2
Portion A
Portion B
Connector 1
GUIDE,PAPER
EXIT
(6P100)
GUIDE,PAPER
EXIT
(6P100)
GUIDE,CASSETTE
R
(3B100)
GUIDE,CASSETTE
R
(3B100)
Connector 2
Hole 4
Hole 5
Fig. B
Fig. 3-14-2