When poor leveling happens, adjust the position of fasteners to fix the mounting
bracket.
After fixing the steel band, push the remainder of band inside the mounting
bracket
Lifting HRU
To lift the HRU, do the following:
1
Tie the rope in two carrying points of HRUs.
Figure 31.
Lifting HRUs (1)
2
While Operator A hauls the rope to carry up the HRUs, Operator B pulls the
rope outward, so that HRUs do not hit the tower platform.
3
Operator C locates the carried HRU to the installation position.
[Rear Side]
Carrying Point_1
For Eye Bolt
Carrying Point_2
For Handle
Carrying Point_1
For Eye Bolt
[Rear Side]