Assembling formwork
Unless stated otherwise, all dimensions are given in mm.
Step 13
Attach a suitable sling, e.g. a two-strand chain sling, to the lifting devices.
Step 14
Working from the advancing side, release the PLATINUM 100 Tie Rods G2 from the tie
rod holder and slide them through the PLATINUM 100 Tie Nuts Closing Side. Screw the
tie rods all the way into the PLATINUM 100 Tie Nuts Advancing Side on the opposite
of the formwork. Screw the counter nut from the PLATINUM 100 Tie Rods G2 onto the
thread of the PLATINUM 100 Tie Nut Closing Side.
Pin clip
PLATINUM 100 Tie Nut
Advancing Side
Tie rod
When the tie rods hit the pin clip of the opposing tie nuts, the tie is ready to take ten-
sion loads but not compression loads. The counter nut cannot resist both tension and
compression loads until the counter nut is tightened.
Summary of Contents for Huennebeck MANTO G3
Page 1: ...MANTO Large frame panel formwork User guide...
Page 9: ...9 Unless stated otherwise all dimensions are given in mm MANTO...
Page 61: ...61 Unless stated otherwise all dimensions are given in mm MANTO MANTO G3 M MANTO G3 M...
Page 219: ...219 Unless stated otherwise all dimensions are given in mm MANTO...