5.
The SLED Transition Kit include 2 stiffening beams, the 3.6m long U-shaped beams shall be installed at the
first 2 HV2 Barrier joints adjacent to the SLED Crash Cushions. A single ¾”-10 x 11” hex head Bolt secures
each Beam in place, installed in the centre of the beam under the HV2 Connectors through the gap between
the Barriers. Washers are to be installed each end and a Nyloc Nut is to be used.
Maintenance and Repair
No ongoing maintenance is required for the Saferoads HV2 Safety Barrier. Barriers should be inspected regularly, and
any damaged segments should be replaced immediately. Damaged barrier segments can be removed and replaced
from between undamaged segments. Repair of barriers is not recommended.