MAX100/200-OPERATION Rev200813
27
8. SETUP
Setup Guidelines
Initial Setup
The AccuMax foam proportioning system must be properly setup before any operations can take place. AccuMax
setup is conducted using Display Modules for either Fury (MAX100) or Fusion (MAX200) models. All settings and
options can be set from within the Menu system.
All systems are built and sold by FoamPro are factory preconfigured to be functional and tested. Installer must verify
system setup after installation. Setup is also needed if hardware configuration is changed or main components are replaced.
Some settings required by the system cannot be set at the factory and must be entered by the installer.
NOTE: Some settings in setup are protected from unintentional change. In order to gain access to these settings
please log in with access code as described in: User Access Level.
Tasks Accomplished During Configuration:
•
Set identifiers to all devices that are parts of the system
• Associate display modules with corresponding injectors/valves to be controlled
• Set values of operating parameters for the system
•
Enable / disable system features based on hardware configuration
• Set user parameters to suit operator’s preference
NOTE: Setup must be followed by system calibration (see Maintenance / Calibration).
AccuMax Setup Guidelines
The following table outlines the order and steps for the typical AccuMax system setup process. Additional steps
may be required for more complex installations. The system could be further customized to suit the operator’s preference
with the ‘USER SETTINGS’ menu.
NOTE: Before proceeding with setup make sure that all electrical connections were made, CAN network terminating
resistors were installed and all devices receive electrical power.