Installation Directions

 

 

1.

 

The Color Light Stream Lighted Bubbler is designed to be installed during the gunite phase 
of the pool building 

2.

 

Two conduits should be run to the bubbler: 

a.

 

2 – 1 ½” PVC pipe for water supply. 

b.

 

2 – ¾” conduit for fiber.

 

 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

3.

 

The water supply pipe should have a gate valve or ball valve installed to adjust the water 
supply flow 

4.

 

The conduit for the fiber optic cable should be run to the Color Light Stream Mini Deck Box, 
no more then 20’ from bubbler. 

5.

 

Prepare a location by digging a hole 2 feet in diameter and depth. 

a.

 

For in deck applications – Level the lid to the finished grade level of decking. 

b.

 

For planter areas – Deck Box lid should be 2 inches ABOVE the landscape area 
to prevent materials from intruding or washing the deck box. 

6.

 

Place deck box into the excavated hole with one of the connection holes pointed in the 
general direction of the conduit for the 12VAC wire to run in. 

7.

 

The bottom of the deck box can be supported by utilizing the 1” PVC support connection.  
The support pipe should be approximately 4” in length.  You may also support the deck box 
to any decking rebar to help maintain the proper level by using the rebar support (4) wings on 
the deck box. 

8.

 

IT IS IMPERATIVE THAT ALL COLOR LIGHT STREAM DECK BOXES HAVE 
PROPER DRAINAGE.  Install 1’ PVC on the bottom of the deck box into the drainage hole 
provided. 

Water

4” – 8”