Ruijie RG-S6250-48XS8CQ Series Switches Hardware Installation and Reference Guide
Product Installation
- 23 -
After equipment is installed, verify if the front/back cabinet doors can be closed.
Verify that the cabinet has been fastened completely, and does not move or tilt.
Verify that the equipment has been installed in the cabinet, and all the cables have been fastened to the cabinet.
Verify that there is sufficient space around the device, especially in the front and at the back of the device (at least
20cm).
Verifying the Cables
Verify that the fibers and twisted pairs match the ports.
Verify that the cables have been bound properly.
Verify that the cabling specification and connecting method are correct.
Verify that the cablings are all indoor. If any outdoor cabling is found, check the connection to lightening protection
power strip of AC power or lightening arrester of Ethernet port.
Verifying the Power Supply
Verify that the power cables are in good contact and comply with the safety requirements.
To avoid body injury and components damage, cut off power supply before checking the installation.