Installation Instructions
Roxtec B frame
For correct casting of frames
into concrete walls, casting
moulds in cellular plastic are
available.
Frame Assembly
Remove the protective foil from the
sealing strip on every short side.
Assemble the frame by inserting the bolts and tighten the nuts. The frame
can easily be assembled around already routed cables or pipes.
Installation, Casting
Before concrete is poured,
the frame and casting mould
is fixed in position with the
frame flange inside the wall.
To be able to make a correct
installation the size of the
opening in the wall must be 5 mm
(0.197") wider than the inside
dimensions of the frame on all
sides. The reason for this is the
fact that the stayplates need this
space to be able to move inside
the frame during installation and
compression.
The B frame cast and sealed in
concrete wall.