4 Start-up
22
FA ROTEX ESU - 07/2008
4.2
Checklists for start-up
Checklist before start-up
1.
Is the ROTEX ESU properly installed in accordance with a permitted set-up and without any discernible damage?
Yes
2.
Does the mains connection conform to the specifications?
Yes
3.
Is the mains voltage 230 V, 50 Hz?
Yes
4.
Is the storage tank filled with water to the overflow point; is the overflow pipe properly connected and sealed?
Yes
5.
On restoration: Has the heat distribution network been cleaned? Is a dirt filter installed in the heating return flow?
Yes
6.
Is a membrane expansion tank mounted according to specifications and in the requisite size?
Yes
7.
Is the safety valve connected to a free outlet?
Yes
8.
Is the system water pressure within the green range?
Yes
9.
Are the heat generator and heating system vented?
Yes
10. Are all sensors connected and correctly positioned?
Yes
11. Are the mixer group and mixer circuit sensor (optional) properly connected to the circuit board?
Yes
12. Is the room thermostat (optional) properly connected and are the corresponding parameters set correctly in the control?
Yes
The system may only be started up if all questions can be answered with "Yes"!
Checklist after start-up
A
Is the circulation pump running; is the heating system warming up?
Yes
B
Has the 3-way diverter valve connector been plugged on following start-up?
Yes
The system may only be handed over to the user/owner if all questions can be answered with "Yes".
• Fill in the supplied installation and instruction form jointly with the user/owner.