To Copy an ME Using the Control Panel
Note:
You must have at least a 2 ME control panel to perform
an ME copy from the control panel. If you only have a 1 ME
control panel, you must perform the copy from DashBoard.
This procedure copies the contents of ME 1 to ME 3 as
an example. Use the same procedure for any ME
combination.
1.
Press and hold the
BKGD
button on the
transition area of the ME that you want to copy
to.
This is the destination ME that you want to copy
to.
2.
Press the
BKGD
button on the transition area of
the ME you want to copy.
This is the source ME that you want to copy
from.
To Copy an ME Using DashBoard
1.
On the
Live Assist
node, click on the
ME Copy
tab.
2.
Click a
Source
button to select the ME you
want to copy.
3.
Click a
Destination
button to select the ME
that you want to copy to.
4.
Click
Copy
.