6
Rosco Maximizer 2B Asphalt Distributor
6-45
Operation
5 Connect the loading hose to the Transfer Line
coupler on the distributor and to the storage tank
coupler Use the over-center latches to secure
couplers
Do not open the Transfer Valve
until transfer line is in place . Failure to follow this
procedure could result in serious burns to the
operator from hot asphalt in the lines . The Transfer
Valve must be opened and closed manually .
6 Open the valve on the storage tank and the Transfer
Valve
7 Set the Plus One Controller Mode Selection button
to the HANDSPRAY/UNLOAD mode
8 Put the Pump Control switch to FRONT Priority
NOTE: If the Rear Controller is used, set the in-cab
controller to Rear Priority mode
9 Run the Manual Pump Speed control in the
FORWARD direction at 50 - 150 GPM (189 3 - 567 8
LPM)
10 When the tank is empty, immediately close the valve
on the external storage tank and stop the pump
11 Open the vent valve to relieve pressure in the line
12 Reverse pump at 50 GPM for 10 seconds to be sure
all pressure is released Close Transfer Valve
13 Slowly remove loading hose
Some residue will remain in the line .
Always wear protective clothing, gloves and a face
shield . Contact with hot asphalt can cause severe
burns .
14 Install the cap on the Transfer Line Secure with the
over-center latches
15 Set the Plus One Controller to Clean-out mode and
follow instructions for Clean-out Mode earlier in this
section
Unloading Mode
Follow these procedures when unloading excess
asphalt from the Maximizer 2B Review these
instructions and follow them to insure the safety of the
operator and to maintain a safe working environment
Be sure that the material in both
tanks is compatible (see
Material Considerations
in
Section 4) . If material is not compatible or if you are
not sure, do not transfer!
1 Check the temperature of the material in the tank
Be sure that it is hot enough to be transferred
without setting up in the transfer lines or the pump,
(see
Material Considerations
in Section 4)
NOTE: If the temperature is marginal or material is
starting to set up, fill the tank with fresh, hot
material to heat it Set the Mode Selection switch
to TANK CRCLT for 5 minutes to mix and heat the
remainder before unloading
Heat material before moving the unit
next to storage tanks . Some asphalt materials emit
flammable vapors that can be ignited by the burner
flame and cause an explosion.
It may be necessary to operate the
burners to heat the tank prior to unloading . In this
case, be sure that the fire tubes are covered with
at least 8 inches of material, (see
Burners & Torch
Operation
in Section 6) .
Do not operate burner equipment when
the vehicle is being loaded or unloaded. The flue
tubes could be exposed causing an explosion inside
the tank, or the material could ignite, causing a fire.
2 Move the Maximizer 2B to the unloading site
Do not open the Transfer Valve
until transfer line is in place . Failure to follow this
procedure could result in serious burns to the
operator from hot asphalt in the lines . The Transfer
Valve must be opened and closed manually .
Check the storage tank for
condensation . If necessary drain the storage tank
before unloading the Maximizer 2B .
3 Check the Transfer Valve and be sure that it is
4 Remove the Transfer Line cap
Return to