Steps to Perform Following Installation
47
2. Installation and Setup
2. Installation and Setup
Push the coolant tank toward the back of the machine.
Push the coolant tank to the point where you feel a click.
Make sure that the coolant tank is touching the back of the machine tightly.
Close the bottom cover.
This completes the filling of the coolant tank.
Continue on to "STEP 3: Spindle Run-In (Long)."
STEP 3: Spindle Run-In (Long)
Close the front cover and turn on the power.
Move the coolant tank slowly. Forcefully moving the coolant tank may cause the coolant to
spray out.
Hold this with
both hands.
Click
Do not push the tank using the bottom-
cover.