Preparing the EUT
1. Set channel 1 of the DC power supply to 3
V, current limit 10
A.
2.
DANGER!
Do not connect the R&S
ESH3-Z6 to mains voltage for the test. Con-
necting the R&S
ESH3-Z6 to the mains voltage poses hazardous or even life-
threatening risks to the operator.
Arrange the test setup for X1.2 - X2.2 bolts as shown in
The current conductors connect to output slots of power supply. The voltage refer-
ence conductors connect to the reference slots (signed SENSE) of power supply.
3. Tighten the torque of M8 nuts: 8
Nm to 10
Nm.
4. Turn on the DC power supply.
DC power
supply
DMM
R&S ESH3-Z6
X2.1
X2.2
X1.1
X1.2
X3
+
+
Power in
RF out
Power out
Figure 5-2: Test setup for GND resistance check
Performing the test
► Read out the voltage of the PE conductor on the digital multimeter.
The GND (PE) resistance must be
≤
6
m
Ω
.
Note:
Calculate the GND (PE) resistance from the voltage drop at the test current.
5.2.2
Power Conductor Resistance Check
Test equipment
●
DC power supply
●
Digital multimeter
●
2x power supply cable
Preparing the EUT
1. Set the DC power supply to 3
V, current limit 10
A.
2.
DANGER!
Do not connect the R&S
ESH3-Z6 to mains voltage for the test. Con-
necting the R&S
ESH3-Z6 to the mains voltage poses hazardous or even life-
threatening risks to the operator.
Perfomance Test