Access Procedures
Chapter 3
11.
Remove the four M12 bolts and washers that secure each of the U and W
phase AC input terminal busbars to the input busbars and carefully slide
the terminal busbars up until the AC current transducers can be removed
from the busbars.
Install the AC Current Transducers
Install the AC current transducers in reverse order of removal.
•
Tightening torque for the M12 bolts is 45 N•m (398 lb•in).
•
Verify that signal wire that was disconnected from the U and W phase
busbars when removing the current transducers is reinstalled.
11
Signal wire
U phase busbar
W phase busbar
Slide busbars up until AC current
transducers can be removed