Rockwell Automation Publication D2-3518-4 - January 2020
53
Chapter
7
Using the Start-up Routines
For standard applications, the start-up routines on the OIM enable you to
configure the most commonly used parameters through a series of steps. This
helps you set up the drive as quickly as possible.
For advanced applications, you may need to adjust additional parameters in the
parameter list using either the OIM or VS Utilities software.
Preparing for Startup
Before performing the start-up routine, you must:
• Be qualified to configure the drive and be familiar with the operation of
AC drives.
• Be familiar with the operation of the OIM.
• Have completed all hardware installation.
• Properly connect the drive to the motor.
ATTENTION:
Only qualified electrical personnel familiar with the construction
and operation of this equipment and the hazards involved should install, adjust,
operate, or service this equipment. Read and understand this chapter in its
entirety before proceeding. Failure to observe this precaution could result in
severe bodily injury or loss of life.
ATTENTION:
Incorrect values for some of the parameters in the start-up
routines can cause the drive to operate improperly. Verify that the values of
these parameters are appropriate for your application. Failure to observe this
precaution could result in bodily injury.
Summary of Contents for Allen-Bradley LiquiFlo 2.0
Page 1: ...LiquiFlo 2 0 AC Drive User Manual OriginalInstructions ...
Page 6: ...6 Rockwell Automation Publication D2 3518 4 January 2020 Table of Contents Notes ...
Page 8: ...8 Rockwell Automation Publication D2 3518 4 January 2020 Preface Notes ...
Page 12: ...12 Rockwell Automation Publication D2 3518 4 January 2020 Chapter 1 Introduction Notes ...
Page 34: ...34 Rockwell Automation Publication D2 3518 4 January 2020 Chapter 2 About the Drive Notes ...
Page 68: ...68 Rockwell Automation Publication D2 3518 4 January 2020 Chapter 8 Programming Basics Notes ...
Page 267: ......