6
GENERAL
GENERAL
6
TECHNICAL SPECIFICATIONS
DESCRIPTION
7000 ACI PLUS (Hot-cold version)
800
1000
1500
2000
Type of buffer tank
Non vitrified
Tank layout
Vertical
Buffer tank capacity
732
855
1420
2013
l
Diameter with insulation
990
990
1200
1300
mm
Diameter of storage cylinder without insulation
790
790
1000
1100
mm
Height with insulation
1800
2050
2165
2480
mm
Height without insulation
1725
1975
2090
2405
mm
Insulation thickness
100
mm
Maximum operating pressure
6
bar
Maximum operating temperature
99
°C
Net weight with insulation
115
170
185
305
kg
Diameter of sensor socket
8
mm
Discharges according to EN 12897:2006
(
∆
T=45 °C, ambient 20°C and storage at 65°C)
131
139
168
190
W
3,14
3,34
4,03
4,03
kWh/24h
Insulation type
20 mm PEXL + 80 mm Soft PU
DESCRIPTION
7000 ACI PLUS C (Cold version)
800
1000
1500
2000
Type of buffer tank
Non vitrified
Tank layout
Vertical
Buffer tank capacity
732
855
1420
2013
l
Diameter with insulation
850
850
1060
1160
mm
Diameter of storage cylinder without insulation
790
790
1000
1100
mm
Height with insulation
1725
1975
2090
2405
mm
Height without insulation
1725
1975
2090
2405
mm
Insulation thickness
30
mm
Maximum operating pressure
6
bar
Maximum operating temperature
99
°C
Net weight with insulation
101
150
164
279
kg
Diameter of sensor socket
8
mm
Discharges according to EN 12897:2006
(
∆
T=45 °C, ambient 20°C and storage at 65°C)
471
528
726
913
W
11,3
12,67
17,42
21,91
kWh/24h
Insulation type
Soft PU shells
(*)
In accordance with DIN 4708 with a
Δ
T of 20°C (80°/60°C) at the coil.
7
LOCATION OF SENSORS
R
7000 ACI PLUS
buffer tanks incorporate sockets for temperature control sensors.
9
The actual positioning of sensors depends on what components, water connections and control device are installed.
9
The installer is responsible for making all necessary connections to the boiler and solar collectors. Installers must use their
expertise to ensure proper installation and functioning in compliance with all applicable legislation.
9
In case of a probe, any electric junction between probe cable and extensions for the connection to the electric panel must be
soldered and protected with a sheath or a suitable electric insulation.