pag. 44 / 57 0MNMHEM30RUENUB 00
4.5
Start-up procedure
Before starting up the whole system for the first time, some tests have to be performed to check that the UPSs are
connected to each other correctly.
A) open all the switches and disconnectors on the UPSs (SWIN, SWBY, SWOUT and SWMB) and on the battery
cabinets.
B) Close SWMB on one unit and check that on all the units:
The voltage present between the corresponding input and output terminals of each UPS is <2Vac. If not,
check that the UPSs are connected to each other correctly.
Once the operation has terminated, open SWMB.
C) Start up UPS1 by closing SWIN, SWBY and SWOUT. Wait until the message “NORMAL OPERATION”
appears on the display.
After a few moments, messages on the UPS status will start to scroll across the first line of the display panel. These
will include the following message regarding the battery disconnector:
Wait: DO NOT connect the BATTERY
D) Close SWIN, SWBY on all the other UPSs.
E) Check that all the parallel-connected MASTER HE s are on.
close the disconnector or the fuses on the battery cabinets
only when the following message is
shown
on the first line of the display panel:
BATTERY CHARGER OFF
FOR OPERATION WITH A SINGLE BATTERY ONLY
Check the letter “X” on the second line of the display panel:
Example: “UPS type”, “X” OUT=YYY%VA, BATT=YYY%Ah, 5=ON(or OFF)
N.B.: the UPS with a capital “X” (B or P) is the MASTER unit
The “X” on the MASTER unit may be:
X= B, the parallel battery code has already been inserted.
Only the battery capacity value has to be inserted (see below).
X= P the parallel battery code must be inserted by pressing keys 3, 5 in sequence on the control
panel and the code 467123 (repeat the same sequence to disable the parallel).
The UPSs connected to the one in which the code is inserted will be automatically configured through the
parallel cable (the letter “b” will be displayed on all the UPSs).
This configures the value of the battery capacity only;
this value must be inserted on the MASTER
UPS, which will send the information to the other units via the signal cable.
G) Close SWMB of UPS 1 and check that the whole system switches onto the bypass line (the bypass LED on unit1
will flash while it must be on steady on the other UPSs), then open switch SWMB again. Wait a few seconds then
check that the UPS1 returns to “NORMAL OPERATION”.
Repeat this operation for the other units connected.
If this check is positive, close SWOUT on all the units.
Replace the switch block on all the SWMBs so that they are blocked in the open position.
H) At the end of the start-up phase, all the UPSs must be in the “NORMAL OPERATION” condition.
I) Wait approx. one minute from the insertion of the last UPS, then check that with the load not connected the output
power indicated by each unit is <3%.
L) Connect the load in output, wait approx. one minute and then check that the power shared between the various
units is within ±2%.
Summary of Contents for MASTER HE
Page 2: ...pag 2 57 0MNMHEM30RUENUB 00 RPS SpA Viale Europa 7 37045 Legnago VR Italy www riello ups com ...
Page 6: ...pag 6 57 0MNMHEM30RUENUB 00 This page is left blank intentionally ...
Page 25: ...0MNMHEM30RUENUB 00 pag 25 57 This page is left blank intentionally ...
Page 35: ...0MNMHEM30RUENUB 00 pag 35 57 This page is left blank intentionally ...
Page 50: ...pag 50 57 0MNMHEM30RUENUB 00 This page is left blank intentionally ...
Page 52: ...pag 52 57 0MNMHEM30RUENUB 00 This page is left blank intentionally ...