Maintenance 

 

Overflow  valves  must  be  checked  for 
operability  at  regular  intervals  according  to 
the national regulations (in Germany: UVV - 
pressure  vessels,  VBG  17  §  32  and  TRD 
601 sheet 2, paragraph 3.4). 

  The  intervals  for  regular  checks  are  to  be  laid 

down  by  the  customer  in  line  with  the  operating 
conditions. 

  The  lifting  lever 

238 

allows  the  valves  to  be 

actuated  from  outside,  they  then  open  at  the 
operating  pressure  available.  For  lifting,  the  pres-
sure is to be at least 85% of the test pressure. 

  All  repair  work  is  to  be  performed  by  qualified 

personnel using the appropriate tools. 

  For  the  arrangement,  designation  and  item 

numbers of all parts of the valve, see 

Section 10

.  

  Spare parts are to be ordered with all the details in 

acc. with the valve identification. 

  Only original spare parts may be installed.  

 
 

9.1  Screw connections 

  To  prevent  leaks,  a  regular  check  of  the  connec-

tion  screws  make  in  line  with  the  operating  re-
quirements. 
For tightening torques, see 

Section 1.3

  To  prevent  screw  connections  from  becoming 

loose in the event of pressure fluctuations or plant 
vibrations,  we  recommend  the  installation  of  ex-
pansion joints or pulsation dampers. 

 
 

9.2  Cleaning 

 

Prior to starting any repair work, the valve is 
to  be  thoroughly  cleaned.  Even  if  the  valve 
has  been  properly  emptied  and  rinsed,  
residual  medium  may  still  be  found  in  the 
valve, e.g. between the lining and body or in 
the bonnet. 

Plastic  parts  may  absorb  medium  which  gradually 
emerges from the material after cleaning. 
 

 

Wear the prescribed protective clothing!  

 
Overflow  valves  which  have  been  cleaned  with  water 
or  other  media  must  be  dried  before  re-assembly  of 
the parts and installation of the valve in the plant.  
 

 

9.3  Modification of the overflow 

valve 

If  modifications  to  the  valve  are  required,  the 
manufacturer must always be consulted. 

Examples:  Modification  with  changed  test  pressure, 
replacement of the spring or adaption to the mass flow 
by reducing the travel.  

After 

approval 

by 

the 

manufacturer, 

these 

modifications  can  be  performed  either  by  the 
manufacturer  or  by  the  customer  under  the  guidance 
of  a  technical  supervisory  agency  or  any  other 
approval authority.  
 
 

9.4  Adjustment of the test pres-

sure 

  Undo  locking  plate 

539

,  dismantle  lifting  lever 

238 

and unscrew the lifting cap 

535

  Undo nut 

920/3

  Adjust  the  spring  tension  with  the  adjusting  screw 

538 

to the specified test pressure. 

  Counter  adjusting  screw 

538 

with  a  hex.  thin  nut 

920/3

 resp. with centering nut 

555 

(DN 25). 

  Check test pressure. 

  Screw on lifting cap 

535 

and tighten. 

  Insert lifting lever 

238

  Mount locking plate 

539

  Have valve lead-sealed. 

  The data specified in the test certificates are to be 

observed. 

 
 

9.5  Important notes on disman-

tling / installation 

 

 

First relieve the plug 

204

!  

 

  Then  undo  the  screws  between  the  bonnet 

513 

and body 

100

.  

  The  seat  and  plug  could  otherwise  be  destroyed. 

Read the precise instructions in 

Section 9.6

  Always  replace  the  seat  and  plug 

pairwise

  and 

always rework them 

completely

  Reworking  of  the  seat  and  plug  requires  special-

ised knowledge.  

  It  is  therefore  recommended  to  have  this  work 

carried out by the manufacturer. 

  After  dismantling,  check  all  parts  for  wear  and 

damage.  

  Observe sectional drawings in 

Section 10

Summary of Contents for GU/F Series

Page 1: ...ore transport installation operation and maintenance Subject to change without notice Reproduction is generally permitted with indication of the source Richter Chemie Technik GmbH 9530 020 en Revision...

Page 2: ...caps and gaskets 11 6 5 Direction of flow and installation position 11 6 6 Grounding 11 6 7 Installation 11 6 8 Gas tight design Option 11 6 9 Signal transmitter Option 12 7 Operation 13 7 1 Initial c...

Page 3: ...sed face ANSI ISA 75 08 09 2004 class 300 with flanges ASME B16 5 Class 300 raised face Materials Body material Ductile cast iron EN JS 1049 ASTM A395 Lining material PTFE PFA on request non conductiv...

Page 4: ...quence The tightening torques for pipe screws and body screws mentioned must not be exceeded For an exception see Section 8 Flange connection valve pipe is leaking The following tightening torques are...

Page 5: ...emperature diagram 2014 68 EU PED AD2000 DIN EN 16668 metal seat seat plug PTFE carbon ASME B 16 42 metal seat seat plug PTFE carbon DIN EN ISO 15848 1 certificate valid from 29 C to 180 C The diagram...

Page 6: ...Directive DGRL They have a corrosion resistant plastic lining Solids can lead to increased wear damage to sealing surfaces or to a reduction in the service life of the valve The overflow valves are se...

Page 7: ...the valve must be completely filled with medium at all times or else a potentially explosive atmosphere must be excluded by superimposing a layer of inert gas b Discharges outside the valve At the poi...

Page 8: ...ns Never transport the valve using the lifting lever 238 See sectional drawings in Section 10 Transport the valve upright in a box or on a pallet on a soft surface and deposit gently on flat ground Di...

Page 9: ...medium residues in the valve Separate valve materials plastics metals etc and dispose of them in accordance with the local regulations 6 Installation The installation conditions to the AD 2000 Code A...

Page 10: ...ases with a 90 vertical upright pipe bend out of the valve the bend must not be located directly downstream of the valve A horizontal pipe section with a gradient must firstly be installed downstream...

Page 11: ...ews using tooth lock washers One pipe screw per flange is underlaid with toothed disks At the customer s request a setscrew M6 with a hex nut and washer will be provided at each flange as an additiona...

Page 12: ...monitoring Glue in stem extension 805 e g Loctite 638 and secure with a hex nut 920 4 The support lower part 542 is screwed on instead of the cap nut 927 1 Insert the O ring 400 3 Mount support upper...

Page 13: ...valve make sure that all the appropriate steps as described in Section 6 1 to 6 7 and Section 7 1 are repeated 7 4 Improper operation and their consequences Fig 7 The test pressure checked by the man...

Page 14: ...is necessary Medium is escaping at the bonnet Have the hex socket screws 914 1 not been tightened If after tightening the screws tightness still cannot be restored either the plastic lining or the be...

Page 15: ...e material after cleaning Wear the prescribed protective clothing Overflow valves which have been cleaned with water or other media must be dried before re assembly of the parts and installation of th...

Page 16: ...nd screw completely onto the thread of the bellows hand tight Counter the bellows 206 on the reinforced section with a pair of pliers Undo the hex socket screws 914 1 Centre the spring bonnet 513 with...

Page 17: ...s bubble tight 10 Drawings 10 1 Legend 100 Body 117 thrust flange 124 pressure ring 204 plug 205 seat 206 bellows 237 lifting aid 238 lifting lever 305 bearing guide 306 stem guide 307 1 guide bush 30...

Page 18: ...Series GU F Page 18 9530 020 en Revision 15 TM 10477 Edition 05 2022 10 2 Sectional drawing...

Page 19: ...Series GU F Page 19 9530 020 en Revision 15 TM 10477 Edition 05 2022 10 3 Views View X Detail Y upper spring plate Detail Z lower spring plate...

Page 20: ...drilled to ASME B16 5 Class 150 Flanges acc to ASME B16 5 Class 150 or 300 raised face Nominal size DIN EN 558 1 series 1 ANSI ISA 75 08 01 Class 150 ANSI ISA 75 08 01 Class 300 d0 H H1 L L L mm inch...

Page 21: ......

Page 22: ......

Page 23: ......

Page 24: ...om T V S d Industrie Service GmbH Voraussetzung f r die G ltigkeit der Herstellererkl rung ist das Beachten und Einhalten der Betriebsanleitung meet the requirement of the leakage rate La S 10 4 mg s...

Page 25: ...ls The laws are such as the Health and Safety at Work Act ArbSt ttV the Ordinance on Harzadous Substances GefStoffV BIOSTOFFV the procedures for the prevention of accidents as well as regulations to e...

Page 26: ...tamination of the pumps valves and component sent in for repair On the basis of this information for the contractor is it possible to meet the necessary preventive action during the execution of the r...

Page 27: ...ch cleaning method radioactive3 1 if no then forward to D other pollutant 2 Aggregates which are contaminated with microbiological or explosive substances are only accepted with documented evidence of...

Page 28: ...ai Info idexcorp com Internet www richter ct com Richter Pumps Valves Inc 406 State Street Cedar Falls 50613 IA USA Tel 1 319 268 8038 Fax 1 319 273 8157 Email RichterCedarFalls Info idexcorp com Inte...

Reviews: