Elevated Load Cell Stands
12
Visit our website
2.8 Weigh Stand Installation to the Floor
1. Make final positioning adjustments to the weigh stands.
2. Adjust the jack bolts to level the weigh stands.
3. Install the shims to support needed overall height of the weigh stands, as needed.
Figure 2-9. Shim Installation
4. Mark where the concrete anchors will be drilled onto the floor.
5. Drill holes through the concrete anchor holes large enough to allow the concrete anchors to be installed properly.
6. Check that the drilled holes for the concrete anchors are free of debris. Use compressed air to blow out holes as
needed.
7. Install the concrete anchors through the weigh stand bases and into the drilled holes.
Figure 2-10. Securing ELS Weigh Stands
8. Hand tighten the concrete anchor nuts and washers on to the concrete anchors.
9. Make final leveling adjustments, if needed.
10. Tighten the concrete anchor nuts.
Jack Bolt
Concrete Anchor Holes