Red Jacket LPG Premier Installation Manual Download Page 25

Installing A Red Jacket Submersible LPG Pump-Motor Unit

Fitting the Pump-Motor Unit into the Manifold or Storage Tank

21

Fitting the Pump-Motor Unit into the Manifold or Storage Tank

The pump-motor unit should be carefully lifted by suitable means that will provide control and stability while 
lowering the unit through the opening.

Electrical Connection

The electrical path must include a vapor sealing device, such as a compound sealing Y-fitting or EEx cable entry 
between the pump and junction box as per local code regulations.

1.

Disconnect, lock out, and tag the power before starting to service the pump.

2.

Connect the three-phase power supply from the master panel to terminals L1, L2, and L3 in the magnetic 
starter.

3.

Before running the pump, the tank and pump well must contain LPG and be purged of air following 
recommended procedures contained in this manual and per local regulations.

Determining Correct Motor Rotation

Where it is not convenient to predetermine the power supply phase sequence, proper rotation can be determined 
by pump performance. Pump head pressure and capacity will be considerably less than rated when the pump is 
rotating backwards.

Using coded wires, connect a wire from terminal T1 in the magnetic starter to a pump wire in the junction box of 
the appropriate submerged pump. Connect another wire from starter terminal T2 to another pump wire and a third 
wire from T3 to the last pump wire. 

With ample LPG in the tank and pump well, start the pump and take a pressure gauge reading of the pump 
pressure with the ball valve closed.

Next, reverse power leads at magnetic starter. Repeat pressure test, as described above. If results are higher than 
the first test, the rotation during the second test is correct. If the second test gives lower results than the first, 
reconnect the power leads as they were initially (as under test 1) for correct rotation.

Where the power supply has been properly marked L1, L2, and L3 in accordance with accepted phase rotation 
standards, it is possible to predetermine the proper rotation of these units. The pump power leads are color coded 
orange, black, and red, and if connected through the magnetic starter to L1, L2, and L3 respectively, the motor will 
rotate in the correct direction. It is recommended, however, that the performance tests always be made whether or 
not the power supply has been properly ‘phased out’.

Three-Phase Current Unbalance

Three-phase current unbalance is a factor that can result in premature motor failure. It causes reduced starting 
torque, excessive and uneven heating and excessive motor vibration. Therefore, it is important that the electrical 
load to the submersible motor be balanced. After the correct motor rotation is established, the amount of current 
unbalance among the three legs of the power supply should be calculated.

To prevent changing motor rotation when taking these readings, the wires to the pump should be moved across 
the starter terminals by always moving them in the same direction.

Percentage unbalanced = maximum current difference from average current divided by average current times 100. 

As seen in the example in Figure 6, the third connection has the lowest percentage of unbalance and should be 
used to obtain maximum motor efficiency and reliability.

OFF

Summary of Contents for LPG Premier

Page 1: ...Manual No 051 327 1 Revision N Installation Guide LPG Premier LPG Premier MidFlow LPG Premier HiFlow...

Page 2: ...f any damages and or shortages within 30 days of receipt of the shipment as stated in our Terms and Conditions VEEDER ROOT S PREFERRED CARRIER 1 Fax Bill of Lading to V R Customer Service at 800 234 5...

Page 3: ...ump Motor Unit 19 Fitting the Pump Motor Unit into the Manifold or Storage Tank 21 Electrical Connection 21 Determining Correct Motor Rotation 21 Three Phase Current Unbalance 21 Typical System Scheme...

Page 4: ...e 9 Typical Scheme For A Direct Installation With Vertical Submersible Pump Motor Unit 27 Figure 10 Service Parts 31 Tables Table 1 LPG Pump Motor Unit Models 4 Table 2 Recommended Material List for D...

Page 5: ...n through the conduit pipe The conduit pipe is mounted inside the product line and is sealed against the pumped liquid The electrical wires are mounted in a plug pigtail which provides a seal into the...

Page 6: ...apors are extremely flamma ble WARNING Warning Alert read message and follow instructions to avoid serious injury death or substantial property damage TURN POWER OFF Live power to a device creates a p...

Page 7: ...rlocked and are enclosed in a stainless steel shell There is not a requirement for initial bearing running in period for the Red Jacket submersible LPG pumps For all types of Red Jacket submersible LP...

Page 8: ...ion with the pigtail discharge head consists of a metal body Ex d flameproof enclosure and electrical connections The wires in the connectors are cast in epoxy The rotor conductors are copper bars Tab...

Page 9: ...ge using an L1 plug gauge Apply Loctite 565 570 or 577 thread sealant Butane and Propane resistant to both ends of the conduit pipe Direct Installation Installing the submersible pump directly into th...

Page 10: ...stallation of Red Jacket LPG Pump Motor Unit FLANGED VALVE FLANGE VAPOR LINE LIQUID LINE WITH DIRECTION ARROW 4 5 3 4 VAPOR LINE 1 1 4 DISPENSING LINE 9 FILL 2 15 24 2 1 3 18 11 10 17 20 19 15 14 13 2...

Page 11: ...e 5 if applicable 7 Flange 2 8 Kit conduit box 1 Red Jacket 114 115 5 9 Ball valve 2 Argus EK 71 10 Relief valve 1 4 Rego 3127 G 11 Remote control valve 3 4 Argus EK 71 Pneu Electrto 12 Internal bleed...

Page 12: ...ified as an unfired pressure vessel and is designed according to regulations for Pressure Vessels The manifold must be suitable for the type of pump to guarantee the above described minimum requiremen...

Page 13: ...Jacket LPG Pump Motor Unit FLANGED VALVE FLANGE VAPOR LINE LIQUID LINE WITH DIRECTION ARROW MANIFOLD 12a 31 7 8 3 4 VAPOR LINE 1 1 4 DISPENSING LINE 30 15 18 FILL 2 21 33 5 2 1 4 3 34 6 29 24 17 16 23...

Page 14: ...5 2h Regulations 10 Flange 5 11 Ball valve 1 2 Argus EK 71 12 Equalization line acc 8 5 2c Regulations 12a Excess flow valve 3 4 Rego A3272 G if applicable 13 Flange 2 14 Kit conduit box 1 Red Jacket...

Page 15: ...an itemized list for the Figure 3 manifold Figure 3 Horizontal Manifold With Red Jacket LPG Pump Motor Unit 31 Relief valve 1 4 Rego 3127 G 32 Manhole cover NW 420 525 mm 33 Check valve 2 Rego A3186...

Page 16: ...9 Excess flow valve 3 4 Rego A3272 G 10 Flange 5 11 Ball valve 3 4 Argus EK 71 12 Vapor return acc 8 5 2c Regulations 13 Flange 2 14 Kit conduit box 1 Red Jacket 114 115 5 15 Ball valve 2 Argus EK 71...

Page 17: ...the tank and the pressure of the manifold to overcome running dry of the submersible pump by low liquid level and to equalize the pressure during refill of the installation The design of the equalizat...

Page 18: ...etely submerged in the liquid This so called NPSH Net Positive Suction Head is 127 mm 5 inches above pump inlet opening for all types Red Jacket submersible LPG pumps Cavitation is when the liquid flo...

Page 19: ...and it is to be recommended to include in the installation a so called Low pressure Dry Run protection unit preferably based on pressure technology When installed according to the specifications the...

Page 20: ...he manifold s inlet opening 4 Installing the submersible pump directly into the storage tank without a manifold is allowable only when permitted by local regulations In such installations the clearanc...

Page 21: ...2 456 50 5 4 20 8 4 10 4 3 7 P500V17 24 5 0 3 7 3 342 456 50 8 8 33 4 9 5 9 3 7 Part Number Model Weight kg lbs 410687 001 LPG 21 10 21 410687 002 LPG 24 10 21 410687 003 LPG 17 11 24 410686 001 P300V...

Page 22: ...esence of an authorized technician System Description The Red Jacket submersible LPG pump is fitted into the special developed manifold which has to be installed into one of the manholes of the storag...

Page 23: ...sket 1 Pigtail connector 14 AWG 3 meter 10 feet 1 Socket screws and lock washers 5 16 18 inch 4 of each O ring Viton 53 6 x 2 6 mm 2 11 x 0 103 in 1 This Installation manual 1 rj 051 327 fig2 eps Prem...

Page 24: ...ligning the pump shaft with the motor coupling Secure the pump to the motor by using the cap screws and lock washers supplied with the pump Using a torque wrench the screws should be tightened to 28 3...

Page 25: ...ure with the ball valve closed Next reverse power leads at magnetic starter Repeat pressure test as described above If results are higher than the first test the rotation during the second test is cor...

Page 26: ...as been taken in the preparation of this manual Veeder Root shall not be liable for any misunderstanding errors and or loss or defects arising from the use of this manual Design codes and local regula...

Page 27: ...the data in Table 7 System Components List of appurtenances as shown on the typical schemes of LPG service station underground and aboveground storage tank with submersible pump Table 7 Required Data...

Page 28: ...uired Optional 19 Excess flow valve equalization line 3 4 Optional 20 Insulation joint 2 21 Insulation joint 1 1 4 22 Insulation joint 3 4 23 Filling hose 3 4 24 Filling nozzle 3 4 25 Break away coupl...

Page 29: ...e length as short as possible diameter minimum 8 mm 0 31 in Excess flow valve If design required in equalization line minimum 78 liter min 20 gallon min Premier Hiflow Nomenclature LPG500V17 24 Excess...

Page 30: ...Premier Midflow Nomenclature LPG300V17 17 Excess flow valve Inlet minimum 462 liter min 122 gallon min liquid Ball valve 2 Manifold 6 9 in 175 mm minimum Outlet 1 2 in Vapor return line in Excess flow...

Page 31: ...ported by three support arms a the inlet b discharge head and c at the pump flange i e DSI PA PE 4 38 Pipe Isolator Manifold must be installed 4 5 upwards to avoid vapor lock in manifold Table 10 Mini...

Page 32: ...ttings are tight to prevent leaks 2 Fill the tank and manifold with nitrogen until pressure reaches 100 kPa 14 7 psi Relieve pressure until it reduces to 15 kPa 2 1 psi 3 Repeat the filling with nitro...

Page 33: ...and fill the manifold with nitrogen pressure max 1000 kPa 145 psi until you hear the nitrogen bubbling from the inlet of the manifold 6 Close the inlet ball valve and purge connection secure the inlet...

Page 34: ...he pressure gauge in the liquid line when LPG vapor comes out 8 Open the ball valve of the manifold and secure the ball valve against closing 9 Connect the pressure gauge 10 Connect the power cable in...

Page 35: ...equirements the pump motor unit should be removed from the storage vessel and inspected A Red Jacket submersible Premier Premier Mid Flow or Premier Hi Flow LPG pump is not repairable The pump and mot...

Page 36: ...cle tank is full Contents gauge No problem exists Differential Pressure Low Discharge head or pump is loose creating pressure leak Pump motor assembly Pull pump motor assembly check condition of O rin...

Page 37: ...sure in vehicle tank Vehicle tank temperature Cool tank or reduce number of open nozzles Pump Not Running Contactor coil is not engaged Emergency stop dispenser switch and contactor wiring Close all s...

Page 38: ......

Page 39: ......

Page 40: ...For technical support sales or other assistance please visit www veeder com...

Reviews: