CHAPTER
1
Manual No. 016-0171-219 Rev E
1
CHAPTER 1
INSTALLATION
PREPARATION
1. Test the existing SCS control system to ensure all product control hardware is operating properly. Repair or
replace any faulty components of the product control system before proceeding.
2. Copy the calibration values from the existing SCS console.
NOTE:
Calibration Values are stored on the existing SCS console and must be programmed into the new
product control console before the Switch Pro system is ready to operate. The following values are
required for Switch Pro operation:
•
Speed cal
•
Boom cals for each configured boom section on the existing SCS control system
The following are required for each product:
•
Meter cal or product density
•
Valve type
•
Valve cal
•
Rate cal(s)
•
Spreader constant (granular systems)
3. Verify that the existing SCS console cable has been installed properly. Refer to the Best Wiring Practices section
on page 4 section later in this chapter for more information.
If an existing Raven SCS 440, 450, 4400 system has not previously been installed prior to purchase of the Switch
Pro system, additional cabling and hardware will be required when installing the Switch Pro system. Please
contact a local Raven dealer for specific flow control components required and installation assistance.
4. Disconnect the SCS console from the console cable and remove from cab.
5. Remove any existing auxiliary section switches.
NOTE:
If existing section switch hardware cannot be removed, the auxiliary section switches must be in the
Off position to allow Switch Pro to operate properly.
If a Remote Master Switch will be used with the Switch Pro, both master switches must be in the Off
position to turn off booms. Toggling either the Switch Pro master or the remote master will enable
boom sections.
6. Remove any mounting hardware or brackets for the existing SCS control console. The machine is now ready for
installation of the Switch Pro system.
Summary of Contents for Switch Pro
Page 17: ...13 FIGURE 2 Viper Pro with Switch Pro for SCS 440 450 Cabled Systems...
Page 19: ...15 FIGURE 4 Viper Pro with Switch Pro for SCS 4400 Cabled Systems...
Page 21: ...17 FIGURE 6 Viper Pro with Switch Pro Combo Cable for SCS 440 450 Cabled Systems...
Page 23: ...19 FIGURE 8 Viper Pro with Switch Pro Combo Cable for SCS 4400 Cabled Systems...
Page 24: ...APPENDIX B 20 Raven Switch Pro Installation Reference Manual...
Page 28: ...APPENDIX C 24 Raven Switch Pro Installation Reference Manual...
Page 30: ...Index 22 Raven Switch Pro Installation Reference Manual...