6.

 

Inspection & Periodic Maintenance 

 

The disc coupling can be monitored under running condition as well as under idle condition.

 

 Inspect the coupling once1 in 6 months in idle condition or whenever it is taken for 
periodic maintenance.

 

 

During running condition, it is recommended to check the vibration and noise of bearings on 
either side of the equipments to be under specified limits.

 

 

Special attention to be given to blade assembly (flexible element) whether is there any wavy 
formation of the blade (“S” or “D” type waviness), this may result in weakening of the flexible 
element under continuous operation. Also check the blade assembly individual elements of any 
fracture or tearing of any blades. If found then it is recommended to replace the entire blade 
assembly at one short. Slight bowing or “S”/”D” like distortion/waviness is not detrimental to 
the operation of the unit. 

 

Check the flexible elements, by visual inspection, for any signs of fatigue failure or cracking to 
the washer anchoring points or general signs of fretting corrosion. Note that any cracking will 
begin at the outermost edge of the outside blade. This means that, this inspection is still 
possible without disturbing the element bolting. 

 

 It is recommended to replace cleveloc nut after being re-tightened 4 to 5 times.

 

 

To replace blade assembly, follow procedure as per section 4.1.

 

7.

 

Spare Management & Complaint Handling 

 

 

7.1

 

Spare management 

 

We recommend to store spare items as given below, inorder to have continuos  operation 
and to reduce down time due to failures. 

 

Spare component list.(Fig.1) 

Sr.No. 

Part descriptions 

Components/ 

part No. 

Quantity 

Element blade assembly 

02 

2 Nos 

Coupling bolt 

01 and/or 11 

6 Nos 

Hub ( I,II) 

03 and/or 09 

1 Nos 

 

Don’t forget to mention hub type while giving spare order for hub and/or coupling 

bolt 

7.2

 

Complaint Handling 

 

In case of any failure,for proper root cause, fill up Product Performance Datasheet (PPDS) 
and provide us alongwith  images/videos.  

 

Summary of Contents for DISC-O-FLEX RLM

Page 1: ...RATHI TRANSPOWER PVT LTD Gaia Apex S No 33 2D Viman Nagar R II D 03 02 09 20 Pune 411014 INDIA Installation Operating Manual IOM DISC O FLEX Coupling RLM RLMK Series...

Page 2: ...neral Guidelines 02 2 Before installation information 02 3 Installation Information 03 3 1 Hub Mounting 03 3 2 Shaft Alignment 05 3 3 Final Assembly 06 4 Disassembly Replacement 07 5 Safety General Ha...

Page 3: ...provides detail information of the design and connected equipments Symbol description Caution person may get injured Damage the product Pay attention Potentially explosive warning 2 Before installatio...

Page 4: ...er Finish bore strictly done within specified limit H7 Js9 Keyway must be done between two adjacent holes Provide set screw at distance L L LTB 2 3 2 Hub Mounting 3 2 1 Clean protective coatings lubri...

Page 5: ...shaft Immediately slide expanded hub over the shaft up to desired position Fig 3 Tighten the set screw with torque wrench 3 2 5 Taper Bore Fig 5 Slid the hub over the shaft without inserting key up to...

Page 6: ...f maximum misalignment Refer Table 3 Table 2 Method of misalignment Method Parallel Radial Angular 1 Using dial gauge Using dial gauge Clamp dial gauge on driven hub Note the reading at each quarter r...

Page 7: ...4 2 RLMK The large holes of Hub II should be in line with the small holes of Hub I Insert coupling bolts from driven hub side through small hole and small length sleeves from driving side Insert coup...

Page 8: ...hat the blades should not be under stresses due to external loads such as spacer weight Dismantle components by loosening coupling bolts 1 from hub Remove cleveloc nuts 7 bushing and blade pack 4 4 1...

Page 9: ...Check all the bolts are tightened as per torque specified in the manual or as specified in the GA drawing The supplied coupling may have to rotate at high speed it is most important to guard the area...

Page 10: ...r S D like distortion waviness is not detrimental to the operation of the unit Check the flexible elements by visual inspection for any signs of fatigue failure or cracking to the washer anchoring poi...

Page 11: ...Installation Operating Manual DISC O FLEX RLM RLMK RATHI TRANSPOWER PVT LTD Gaia Apex S No 33 2D Viman Nagar R II D 03 02 09 20 Pune 411014 Page 10 of 15 Product Performance datasheet PPDS GO TO INDEX...

Page 12: ...Installation Operating Manual DISC O FLEX RLM RLMK RATHI TRANSPOWER PVT LTD Gaia Apex S No 33 2D Viman Nagar R II D 03 02 09 20 Pune 411014 Page 11 of 15 GO TO INDEX...

Page 13: ...ture shaft bearing failure Excessive misalignments Check for loose base plate bolts Component thermal expansion Change in the assembly gap of the coupling Replace the Blades 2 Fatigue of Blades Torsio...

Page 14: ...ATEX marking for REM coupling will be given on outer surface or front side Fig 8 Element blade assembly will not be marked Example Fig 8 Marking example ATEX Punching sample 1 RATHI DISC O FLEX 120 R...

Page 15: ...Installation Operating Manual DISC O FLEX RLM RLMK RATHI TRANSPOWER PVT LTD Gaia Apex S No 33 2D Viman Nagar R II D 03 02 09 20 Pune 411014 Page 14 of 15 GO TO INDEX 10 Declaration of Conformity...

Page 16: ...Installation Operating Manual DISC O FLEX RLM RLMK RATHI TRANSPOWER PVT LTD Gaia Apex S No 33 2D Viman Nagar R II D 03 02 09 20 Pune 411014 Page 15 of 15 GO TO INDEX...

Reviews: