23
Inspection of the waste gas system
The inspection with regard to problem-free waste gas
flue in the waste gas system must be carried out under
the following operating conditions.
– Windows and doors in the boiler room must be closed.
– The required ventilation provisions may not be shut,
re-positioned or narrowed.
– The recommended chimney flue must be 0.03 mbar
minimum and may be 0.1 mbar maximum.
– In the event of the chimney flue exceeding 0.1 mbar
consult the district master chimney sweep concerning
corrective action (e.g. fitting in a flue reducer).
8
Wiring
Before starting any work on the electrical wiring
all cables must be voltage-free. The connection
to the mains must be established over a fixed
connection and a splitter (e.g. fuses, LS-Switch).
The boiler must be earthed by connection to the
mains.
Ensure that the installation is in phase when
connected to the mains. Phase and neutral
conductor must not be interchanged (see the
inscription on cover or circuit diagram). Mains
and sensor connection leads must not be jointly
led through one single tube or cable harness.
Instruction:
The lower value should not be lower in view of
the problem-free waste gas flue and the upper
value should not be exceeded in view of proper
operational level.
Environment:
The lower the chimney flue (within the permitted
boundaries) the better the pyrotechnic operation
level of the fire place.
Carry out the waste gas loss measuring in accordance
with BlmSchV under the aforementioned operating
conditions.
8.1 Boiler sensor connection KF
(supplied package rapidomatic
®
)
– The boiler sensor is fitted into distributer pipe
(see Fig. 3.).
distributer pipe
Fig. 3