PIPES - CORRECT INSTALLATION
F.7.1
FLUID PRODUCTS
Set up the pump at the minimum distance from the suction tank
(inlet).
Arrange the delivery pipe (outlet) at an angle to facilitate the
discharge of the pumped fluid
F.7.2
VISCOUS PRODUCTS
Set up the pump in positive suction head condition.
For pumping of corrosive or hazardous substances the pump must
be installed in a containment compartment.
F.7.3
OVERPRESSURE
If the delivery pipeline includes the possibility of a shut-off valve, it
is necessary to install a pressure control system or a bypass.
The same hazard may exist on the suction pipe in the event of
reverse flow.
F.7.4
PUMP STOPPED
With positive H, the fluid continues to flow into the pipe: avoid with
appropriate valves.