Chapter 2 Basic Library Operations
Preparing the Library for Operation
Quantum P4000 and P7000 Libraries User’s Guide
37
Preparing the Library for Operation
2
To prepare the library for operation:
• Close the library doors and access panels
• Connect the host workstations
Closing the
Library Doors and
Access Panels
2
The library has two front doors (P7000 only) and three back access panels.
1
Close and lock the front doors.
a
Close one door and then the other.
b
Turn the door latches to secure the doors to the library frame.
c
Lower the latches over the door locks.
d
Using the key from the accessory kit, lock the latches in place.
2
Close and lock the back access panels using a 5/32 hex wrench (not
provided).
Connecting Host
Workstations
2
Connect the SCSI (or Ethernet) cables and jumpers as shown in the
applicable figures.
shows the recommended cabling configuration for a 8-drive
P4000 library.
shows the recommended cabling configuration for a 16-drive
P7000 library.
shows the Ethernet cabling configuration for a 10-drive P4000
library.
shows the Ethernet cabling configuration for a 16-drive P7000
library.
Note:
Quantum ships sufficient SCSI cables and terminators with
this library to set up two-drives per SCSI bus, as well as
adequate SCSI jumper cables to accommodate up to 4 drives
per SCSI bus.