SECTION 6 – COMMISSIONING
QUANTECH
106
Sporlan EEV Interface Board
Verify the jumper and dip switch settings, shown in
Figure 35 on page 106, during a chiller start-up for
YLAA, YCWL and QWC3
chillers with Sporlan Elec-
tronic Expansion Valves.
With the IB-G unpowered, select the input signal of
0-10V by installing the supplied jumper to number 1
of the 5 pin locations shown in the left hand side of
EEV board. Set numbers 1 to 3 of the DIP switches
in accordance with the unit models. Set numbers 4 to
8 in accordance with the table shown in
. For YLAA, YCWL and QWC3 chillers,
DIP switch number 6 must be set to ON for a quicker
EEV response.
Grounding
Verify that the unit’s protective ground terminal(s) are
properly connected to a suitable grounding point. En-
sure that all unit internal ground connections are tight.
Supply Voltage
Verify that the site voltage supply corresponds to the
unit requirement and is within the limits given in the
Technical Data Section.
LD23530
FIGURE 35 -
EEV IB-G INTERFACE BOARD
DIP SWITCH
NUMBER
YLAA0230
ALL OTHER
CHILLERS
1
OFF
OFF
2
OFF
ON
3
OFF
OFF
JUMP
LOCATION
INPUT
SIGNAL
1
0-10 V
DIP SWITCH
NUMBER
ALL
CHILLERS
4
OFF
5
OFF
6
ON
7
OFF
8
OFF
Summary of Contents for QWC3050T-200T
Page 4: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 4 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 10: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 10 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 28: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 28 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 144: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 144 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 152: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 152 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 166: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 166 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 185: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 185 NOTES...