2.Attach a Lambda sensor to the exhaust outlet, at the threaded boss. Turn on the gage and
make sure it is calibrated; the reading should be 20.9.
3. On the Lynx FPC/Config Tab, Set
Head Setpoint to 600°C
and click
Set
.
Figure 12-14 Head Temp Setpoint
4. While commissioning the PowerGen equipped with QEC3.5 the following parameters must
be changed to override the Load-following features of the software. This is mainly to
override the parameters to properly tune the gas valve during commissioning.
5. Under the FPC/Config Tab, Set
Max blower to 80%
, Click Set.
Summary of Contents for PowerGen 5650 Series
Page 1: ...7045 102089 000 June 1 2021 Installation Operation Manual FOR A QUALIFIED INSTALLER...
Page 8: ...iv...
Page 12: ...iv Figure 21 9 ATS Enclosure 179 Figure 21 10 Battery Connection Schematic 181...
Page 28: ...SYSTEM INTRODUCTION 16 Figure 3 6 P ID Diagram...
Page 69: ...QNERGY LYNX SOFTWARE 57 Figure 6 57 FPC FEB QEC Firmware Update...
Page 158: ...MAINTENANCE 146 Figure 17 2 Radiator and Over Flow Tank...
Page 194: ...POWERGEN OPTIONAL FEATURE SETS 182...