P
OWER
G
EN
R
EPORTS
AND
C
HECKLISTS
157
19.3 COMMISSION SEQUENCE
Table 19-4 Commissioning Checklist
Step #
Step
Initials
1
Connect 12VDC Battery in PowerGen
• Connect ring terminal on black wire to the black terminal on the
battery
2
Disconnect customer electrical load
3
Engine Helium Fill (See “Helium Fill” on page 76)
• Connect laptop to FPC via CAN bus cable, use TC1 temperature
reading for Helium Fill)
• Use “Target Charging Pressure” on page 82 for reference or the label
on the engine beam of the system near the helium fill port
Engine Temperature indicated by FPC:
°C
Engine Helium pressure after filling:
PSI/BAR
4
Gas type connected to PowerGen: NG LGP Biogas
Gas static pressure (FPC/Data Tap/Gas Pressure):
mbar
5
Commissioning FPC firmware version (update to
latest):
6
Commissioning QEC firmware version (updated to
latest):
7
Gas Valve Tuning (See “Gas Valve Tuning, PowerGen 5650” on page 83 or
“Gas Valve Tuning, PowerGen 600, 1200, 1800 (Low Temp systems
• 5650 Lambda High Reading (1.18):
• 5650 Lambda Low Reading (1.23):
• 600/1200/1800 Lambda High reading (1.2):
8
GHT VFD Speed Pot Setting as per PowerGen Feature Set Manual,
7045-102-103-000 (if GHT option is installed):
Customer GHT Tube Length:
ft
VFD Speed Setting:
Summary of Contents for PowerGen 5650 Series
Page 1: ...7045 102089 000 June 1 2021 Installation Operation Manual FOR A QUALIFIED INSTALLER...
Page 8: ...iv...
Page 12: ...iv Figure 21 9 ATS Enclosure 179 Figure 21 10 Battery Connection Schematic 181...
Page 28: ...SYSTEM INTRODUCTION 16 Figure 3 6 P ID Diagram...
Page 69: ...QNERGY LYNX SOFTWARE 57 Figure 6 57 FPC FEB QEC Firmware Update...
Page 158: ...MAINTENANCE 146 Figure 17 2 Radiator and Over Flow Tank...
Page 194: ...POWERGEN OPTIONAL FEATURE SETS 182...