2. Safety
8
[Figure 2-3 : PV connections]
To connect Q.HOME+ ESS-G1 3.6 with the Public Grid, make sure to install the watt-hour
meter recommended by Hansol Technics (refer to the installation manual) and to install
the distribution box between Q.HOME+ ESS-G1 3.6 and the Grid watt-hour meter. Before
installing the distribution box, select a suitable location complying with the IP21 and
use the equipment recommended by the installation company. Please note that failure
to do so may cause malfunction and the product will not be guaranteed for any
accident or damage.
Refer to the installation manual for further information. The [Figure 2-4] shows the
complete connection line as described so far.
[Figure 2-4: Distribution box connection diagram]