Commissioning
WARNING!
– Commissioning must be performed by a spe‐
cialist in accordance with DGUV Regulation
103-015.
– Outside of Germany, the regulations applicable
in each respective country for the operation of
ozone generation systems should be observed.
– Persons are deemed to be qualified as tech‐
nical personnel, if they have undergone a
training course from ProMinent and have the
requisite authority.
All warranty and liability claims on the part of the
system operator will not be admitted following
interference by unauthorised personnel.
WARNING!
Unauthorised access to the system or to parts of
the system can endanger life.
Compressed air or pure oxygen and high voltage
are used in the system to generate a toxic gas.
WARNING!
Adjustments may have to be made inside the con‐
trol cabinet during the course of commissioning.
When the system is switched on, the electrical
components inside the control cabinet represent a
source of danger if touched.
– Wait at least 5 minutes after the supply of
power to the plant has been interrupted by the
mains switch before touching the components
on the inside of the cabinet.
Perform a functional test once the system has been installed to
check for any possible damage that could have been caused
during transportation.
Prior to starting up the ozone generation system, ensure that
n
the system complies with local regulations - see "Assembly and
installation" and "Safety” chapters,
n
the requirements relating to the installation place of the system
have been met,
n
the system has been properly installed - see "Assembly and
installation” chapter,
n
pneumatic and hydraulic connections have been made in
accordance with the regulations, are tight and have been pres‐
sure tested,
n
all electrical connections have been made in accordance with
the regulations and an emergency stop switch has been fitted
at the entrance to the plant room,
n
correctly functioning protective equipment is available,
Preliminary tests
Commissioning